Finances

2010 Budget

The 2010 budget was finalized and passed on Thursday April 8th, 2010 - it will be available online shortly.

5 Year Capital Plan

The Municipality has made the following capital purchases in 2008 & 2009:

  • Tractor $60,000.00
  • Office Equipment/Repairs $15,000.00
  • Road Repairs $40,000.00 * Workshop Repairs $7,500.00
  • Laser Transit $7,000.00
  • Water Line Repairs $25,000.00
  • Road Renaming - signs $11,900.00
  • Dry Hydrants $6,000.00
  • Economic Development $10,000.00 While the following is a list of major capital projects planned from 2009-2013

While the following is a list of major capital projects planned from 2009-2013.

    2009 2010 2011 2012 2013
Motor Grader       160,000    
Office Building Roof   10,000        
Mower   15,000        
Joint Hospital           135,000
TOTAL   25,000   160,000   135,000